Bond reduction
Case Study - Section 278 Legacy Adoption
How JLES took on the outstanding Section 278 works at Whitley Business Park, Coventry as specialist contractor and adoption partner, on an adoption-guaranteed fixed fee.

A Section 278 scheme, unadopted since 2008, remediated alongside the A444 in Coventry
ÂŁ156k+
Bond reduction
6 months
Project duration
0 extras
100% fixed fee
40+
Resident liaisons
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Carriageway Resurfacing
Whitley Business Park, Coventry
Section 278 agreement unadopted since 2008 · Coventry City Council TTROs
Whitley Business Park forms a key access route to a busy operations centre in Coventry, and its Section 278 agreement had remained unadopted since 2008. Significant remediation was needed before the scheme could progress, including defective drainage infrastructure, ageing highway assets and outstanding works across a live A-road network.
With the works alongside the A444 in a high-traffic commercial environment, delivery had to be coordinated to maintain access to Jaguar Land Rover, a hotel and a gym, while managing programme risk and disruption.
JLES, appointed as specialist contractor and adoption partner, took full responsibility for delivery and managed the programme end-to-end under an adoption-guaranteed fixed fee, with no client involvement required. The works were completed in 5 months, with traffic maintained throughout and a ÂŁ1.39M bond released.
Drainage remediation
Deep excavations to replace defective laterals and gullies, installation of a pre-cast headwall and replacement sections of the main drainage network.
Resurfacing under night-time closures
Full carriageway resurfacing managed under night-time closures, with TTROs implemented in collaboration with Coventry City Council.
Street lighting upgrade
The full street lighting network upgraded, including new columns, cabling and a feeder pillar.
Highway remedials and landscaping
Kerb replacements, utility cover resets, embankment works and replanting within the roundabout.
Works coordinated with Jaguar Land Rover and neighbouring businesses to minimise disruption.