Bond reduction
Case Study - Section 38 Estate Completion
How JLES took on the outstanding Section 38 works at Oakham, Rutland as a single contractor, on a 100% fixed fee.

A live residential development taken from unfinished roads to a completed highway scheme.
ÂŁ156k+
Bond reduction
6 months
Project duration
0 extras
100% fixed fee
40+
Resident liaisons
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Carriageway Resurfacing
Client: Allison Homes
Oakham, Rutland · Rutland County Council adoption
The unfinished estate was frustrating residents. Ponding in block paving, incomplete carriageway surfacing, excessive footway gradients and drainage defects were all stopping the scheme from progressing to adoption.
Excavation, drainage, block paving, kerbing, lighting and resurfacing had to happen in the right order, to Rutland County Council's standards, while 506 residents kept access to their homes.
Allison Homes now has a completed highway scheme ready to progress to adoption. JLES delivered all outstanding works about one month ahead of schedule across a five-month programme, with one contractor managing every workstream from investigation to completion, on a 100% fixed fee.
Drainage and manhole remedials
8 gullies replaced, 2 new gullies installed, 7 structurally lined, and 23 manholes and 54 gullies raised to level, to the water authority's satisfaction.
Block paving rebuilt
650m² of carriageway reprofiled, 225m² of footways regraded to reduce gradients, 260m² of tables reconstructed and 695m² of new tables laid.
Kerbs and resurfacing
550 kerbs replaced, 460m² of footpaths resurfaced, 730m² of binder course replaced and around 3,700m² of carriageway resurfaced.
Lighting and traffic calming
3 street lighting columns with ducting, road crossings and power connections, plus 9 speed check ramps.
Drainage, block paving and surfacing sequenced as one programme across both phases, delivered right first time.