Bond reduction
Case Study - Section 38 Estate Completion
How JLES took on the outstanding Section 38 works at Peugeot Works, Coventry as a specialist contractor, on a 100% fixed fee.

A large, multiphase residential development taken from outstanding adoption issues to a completed scheme.
ÂŁ156k+
Bond reduction
6 months
Project duration
0 extras
100% fixed fee
40+
Resident liaisons
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Carriageway Resurfacing
Client: Taylor Wimpey
Peugeot Works, Coventry · Coventry City Council adoption
Peugeot Works was a large multiphase development with a long delivery history and evolving Section 38 requirements. Adoption had been delayed for years by construction issues, legal complications, the absence of completed Section 38 agreements and a required redesign of the Peugeot bus gate phase, which was critical to unlocking future phases.
Remedial works, drainage connections and resurfacing had to be completed across five phases, with full road closures coordinated while more than 500 resident liaisons kept access maintained.
Working with Taylor Wimpey and Coventry City Council, JLES' technical and legal teams resolved the outstanding adoption and design issues while the delivery team completed the remaining infrastructure and remedial works. JLES coordinated the legal, technical and on-site requirements as Specialist Contractor on a fixed fee, allowing the development to progress towards final adoption with minimal ongoing client involvement.
Legal and adoption
Short-form Section 38 agreements implemented by JLES' internal legal team, immediate sewer adoption secured under fixed fee S104/185 agreements, and the Section 38 redesign approved with Coventry City Council. A Deed of Dedication removed the need for a high-value bond.
Drainage and remedial works
5m deep excavations and drainage connections, plus sewer cross-connections and street lighting restorations, delivered across five phases of remedial and final surfacing works.
Carriageway and footway reconstruction
Carriageway and footways reconstructed after over a decade of wear and tear, with resurfacing and streetscape improvements completed across the site.
Peugeot bus gate
A phased 4-month programme to complete the bus gate infrastructure, including streetscape reconstruction, full road closures and maintained access for residents.
Legal, technical and on-site delivery coordinated as one programme across all five phases.