Case Study - Section 38 Legacy Adoption

David Wilson Homes: £69,250 bond reduction on a stalled adoption, in 5 weeks

How JLES unblocked the legacy Section 38 scheme at West View with targeted highway remedials, on a 100% fixed fee with zero extras.

New footway surfacing and block paving brought up to the standard Somerset Council requires for adoption.

Ā£156k+

Bond reduction

6 months

Project duration

0 extras

100% fixed fee

40+

Resident liaisons

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.

Carriageway Resurfacing

Client: David Wilson Homes

West View Ā· Somerset Council adoption

The challenge

Adoption had stalled because of poor road construction in the original development. Investigations found inadequate binder beneath areas of sand and block paving, and footpath resurfacing was later flagged as snags. Residents were pressing for adoption, and David Wilson Homes wanted to release the outstanding highway bond.

Somerset Council kept identifying remedial items at inspections, so the site had to be presented in the right condition first time. A nearby school meant works and access had to be managed around busy drop- off and collection times.

The outcome

The previously stalled Section 38 adoption is moving again. The project was worth £23,235 and delivered a £69,250 bond reduction for David Wilson Homes, completed in 5 weeks on a 100% fixed fee with no extras charged.

What we delivered

Targeted highway remedials and redesign

General highway remedial works aimed at the items blocking adoption, rather than blanket repairs.

Block paving and footway reinstatements

Areas with inadequate binder rebuilt, and footpaths resurfaced to clear the snags.

Inspection planning

JLES requested inspection at the right stage and brought the site to a high standard beforehand, reducing the risk of further snagging.

School and community coordination

Works planned around school rush hours, with extensive liaison with 132 residents.

See the difference

Road after the works Road before the works

Block paving reinstatement under way, managed around school drop-off and collection periods.