Bond reduction
Case Study - Section 38 & 104 Estate Completion
How JLES delivered a multi-phased Section 104 and Section 38 estate completion programme at Upton, Northampton, on a 100% fixed fee.

Resurfaced carriageways, granite kerbs and block paved parking bays
ÂŁ156k+
Bond reduction
6 months
Project duration
0 extras
100% fixed fee
40+
Resident liaisons
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Suspendisse varius enim in eros elementum tristique. Duis cursus, mi quis viverra ornare, eros dolor interdum nulla, ut commodo diam libero vitae erat. Aenean faucibus nibh et justo cursus id rutrum lorem imperdiet. Nunc ut sem vitae risus tristique posuere.
Carriageway Resurfacing
Client: Keepmoat Homes
Upton, Northampton · Anglian Water & West Northamptonshire Council
Upton needed a range of sewer and highway remedial works to satisfy the adoption requirements of Anglian Water and West Northamptonshire Council, including drainage repairs, reconstruction of defective manholes, carriageway surfacing and extensive replacement of highway materials, across four agreements and seven contracts.
An unadopted connecting road was managed separately by the Council and its PFI Contractor, and specialist materials had to be sourced from Portugal to match the existing infrastructure.
Working closely with all stakeholders, JLES carried out the technical, legal and construction requirements while liaising with 250+ residents, delivering on a fixed-fee, no-extras basis over 24 months and progressing the development towards final adoption.
Sewer remediation
Manhole reconstruction, buried manhole recoveries, drainage repairs and structural lining works.
Highway improvements
Granite kerb replacement, tactile paving renewals, final surfacing and block paved parking bays.
Specialist materials
Granite kerbs and tactile paving sourced from Portugal to maintain consistency with the existing development.
Fully managed adoption
Adoption coordinated with Anglian Water, West Northamptonshire Council and a third-party PFI Contractor, overseeing the legal, technical and construction work.
Legal, technical and on-site delivery managed as one adoption programme with Anglian Water and the Council.