Monarch Avenue, Peterborough

PROJECT OVERVIEW

Allison Homes appointed JLES Thames as their specialist contractor to complete the outstanding sewer works on this development. JLES’ works programme enabled Anglian Water to issue the schemes maintenance certificate. The works included:

• Manhole works programme which involved; replacing damaged raising pieces, frame / covers, headwall clearance, general maintenance /cleansing.

• Major excavation works programme; 3no surface water and 1no foul water excavation to replace damaged drainage length sections.

• No foul water excavation as per the key features section.

This project was completed on a fixed fee basis with 0 extras charged to the client.

KEY FEATURES

• Allison Homes appointed JLES Thames as the Specialist Contractor on this scheme to finalise the outstanding S104 Legacy Agreement works.

• Extensive foul and surface water sewer excavations to replace damaged drainage lengths.

• Extensive surface water sewer excavations to replace damaged drainage lengths.

• Implementation of traffic and pedestrian management systems.

• Implementation of legal easement with third parties

• Extensive specialist jetting / cleansing and structural lining works

CHALLENGES

• With only one entrance into the estate, JLES engineers had to continually monitor and manage the traffic flow accessing and exiting the development.

• The excavations crossed many residents' driveways, so road plates and extensive liaisons were completed to ensure access was available when required.

• Engineers had to carefully work around difficult utility crossings within the highway when completing a full length re-lay of a foul water sewer.

• Due to the depths of the excavations, we faced multiple complex health and safety issues, which meant JLES engineers had to ensure they were always working to the correct regulations.

PROJECT Statistics

100

%

fixed Fee

£

Contract Value

Extras Charged

60

+

Resident Liaisons

100

%

Reduction on internal resource

4

Months Project Duration
Weeks Project Duration
Carriageway Resurfacing
Weeks Project Duration

£

Bond Reduction

%

Resident Satisfaction
100

Fixed Value

Contract Value

Extras Charged

60

Resident Liaisons

100

reduction on internal resource

4

month project duration

bond reduction

Resident satisfaction

100

%

Fixed fee

Extras charged

£

Bond reduction

60

+

Resident liaisons

100

%

Reduction on internal resource

4

Month project duration

£

Contract value

%

Resident Satisfaction

Client feedback

"I’m so glad we engaged with JLES to progress an old legacy site, to achieve it being placed on to maintenance. From start to finish they carried out the works in a professional manner with consideration to residence and local authorities on a site which had ongoing issues. The works were carried out on a tight program and the service we received was excellent even the contractors on site acted in a professional manner and were courteous to the residents. All the way through we were informed of progress and had regular updates on progression which was concluded by receiving the maintenance certificate only a few weeks after works were completed. We have already stated communication on the next potential contract."

Engineering Manager | Allison Homes