Flambards, Birkenhead

PROJECT OVERVIEW

Flambards, Birkenhead, was an occupied residential development where previously unidentified sewer adoption issues had prevented the drainage network from being brought up to an adoptable standard.

Following discussions between Magenta Living and United Utilities, remedial works were identified as being necessary to enable the sewer network to progress towards adoption. JLES was appointed to provide a fully managed solution, removing the burden from the client team and acting as a single point of contact throughout the process.

Working collaboratively with Magenta Living, United Utilities and all relevant stakeholders, JLES planned and delivered the required remedial works under a fixed-fee agreement, providing complete commercial certainty with no unexpected costs.

Given the location of the works within an occupied residential environment, resident communication and welfare formed a key part of the project. Through proactive liaison and careful management, the works were completed safely, efficiently and with minimal disruption to the local community.

The project was successfully completed on schedule, allowing the drainage network to achieve the required standard for adoption.

KEY FEATURES

• Delivered under a 100% fixed-fee agreement, providing complete commercial certainty and no additional charges.

• Acted as a single point of contact, managing all stakeholders throughout the project.

• Worked collaboratively with Magenta Living, United Utilities and project representatives to progress the site towards adoption.

• Delivered a one-stop-shop solution, combining technical delivery, stakeholder management and resident liaison within a single package.

• Completed 25m of sewer replacement works and associated manhole improvements.

• Undertook excavations up to 2.2m deep within residential areas.

• Extensive resident liaison undertaken throughout the programme.

• Maintained safe access for residents, families and pets during construction.

• Reinstated carriageways, footways and private gardens following completion.

• Returfed affected gardens, leaving properties in an excellent condition.

• Successfully completed works within the agreed programme.

BEYOND THIS PROJECT

JLES supports housing providers and landowners across the UK in resolving infrastructure issues that can create ongoing maintenance liabilities and resident concerns.

By acting as a single point of contact, we manage stakeholder coordination, resident liaison, construction delivery and adoption progression under one fully managed package.

Our fixed-fee model provides complete cost certainty, helping clients demonstrate value for money while avoiding unexpected project costs.

The result is a simpler, lower-risk route to adoption that protects internal resources and allows organisations to focus on their core responsibilities.

PROJECT Statistics

100

%

fixed Fee

25

meter

Pipe Replacement Completed

2.2

meter

Deep Excavations Undertaken

£

Contract Value

0

Extras Charged

+

Resident Liaisons

%

Reduction on internal resource

Months Project Duration
Weeks Project Duration
Carriageway Resurfacing
Weeks Project Duration

£

Bond Reduction

NIGHT TIME

Delivery workscompleted under TTRO closures

LIVE - A ROAD

traffic maintained throughout

%

Resident Satisfaction
100

Fixed Value

Contract Value

0

Extras Charged

Resident Liaisons

reduction on internal resource

month project duration

bond reduction

Resident satisfaction

100

%

Fixed fee

0

Extras charged

£

Bond reduction

+

Resident liaisons

%

Reduction on internal resource

Month project duration

£

Contract value

%

Resident Satisfaction

Client feedback