West View, Creech St Michael

PROJECT OVERVIEW

This complex S278 scheme had many restrictive measures in place & required a large scope of high remedial works in order to get the maintenance certificate released. This involved: 

• Kerb repairs and replacements throughout the development

• Approximately 325M2 of full highway & footpath re-surfacing

• Drainage dig-downs to multiple manholes

• Full resurfacing of traffic calming tabletop to be able to achieve adequate vertical deflection on ramps

• Raising of iron works, gully relocation, gully connection remedials and cleansing

• General site maintenance



CHALLENGES

As well as being located adjacent to a pre-school, this development has only 1 access and egress point and a heavy flow of traffic on the trunk road, therefore the scheme involved:

• Heavily involved health & safety coordinators to ensure all required safety measures where in place

• Due to the location of the junction, extensive traffic management was required to ensure access was available whenever necessary

KEY FEATURES

• JLES Exeter were appointed as the Specialist Contractor on this complex S278 legacy scheme. to acquire the maintenance certificate for their client, David Wilson

• Lump sum, fixed cost to complete S278 works and achieve maintenance

• Works invoiced upon Local Authority written acceptance

• Supervision and management of works throughout

• Consultancy and technical work to satisfy outstanding adoption documentation

• JLES acting as Principal Contractor, Main Contractor & the developers Managing Agent

• Resident liaison & full customer care package

PROJECT Statistics

100

%

fixed Fee

£

Contract Value

0

Extras Charged

50

+

Resident Liaisons

%

Reduction on internal resource

3

Months Project Duration
Weeks Project Duration
Carriageway Resurfacing
Weeks Project Duration

£

Bond Reduction

%

Resident Satisfaction
100

Fixed Value

Contract Value

0

Extras Charged

50

Resident Liaisons

reduction on internal resource

3

month project duration

bond reduction

Resident satisfaction

100

%

Fixed fee

0

Extras charged

£

Bond reduction

50

+

Resident liaisons

%

Reduction on internal resource

3

Month project duration

£

Contract value

%

Resident Satisfaction

Client feedback